An NGED grid connection application is a G99 application form plus site plans, a single line diagram and, for projects over 1MW, evidence that you have the land. NGED must send a formal connection offer within 45 working days at low voltage and 65 working days at high voltage or above. You then have 90 days to accept it.
Who NGED is
National Grid Electricity Distribution (NGED) runs the local electricity network across the Midlands, South Wales and the South West, from the Lincolnshire coast to the Isles of Scilly. It used to be called Western Power Distribution. It is the largest of the six network operators in Great Britain, serving about 25 million people. If your site is in that area, NGED is who you apply to.
Budget estimate or formal connection offer?
| Budget estimate | Feasibility study | Formal connection offer | |
|---|---|---|---|
| What it is | A desktop cost guide. No network studies. | A closer look at whether a connection is possible. | A full offer with a cost, date and connection point. |
| Cost | Free | Chargeable | Assessment and design fee (see below) |
| Can you accept it? | No | No | Yes. It becomes a binding contract. |
| How long | 10 working days (under 1MVA), 20 working days (1MVA or more) | Agreed case by case | 45 to 65 working days (see timescales) |
A budget estimate is a good first check, but it leaves out network reinforcement, so the real offer can cost a lot more. Bigger projects can also book a “connections surgery” with a local planner.
How to apply for a grid connection with NGED
For generation and batteries, the G99 standard application form is your connection application. Send it by email or post to NGED’s regional office. You will need:
- Location plan and site layout plan, showing where the connection is needed.
- Capacity: how much you want to export and import, in kW or MW. Batteries count as generation.
- Technology and equipment data: G99 Part 3, plus Part 4 model data, and inverter or turbine spec sheets.
- A single line diagram: a simple drawing of the electrics on site.
Since January 2025, projects over 1MW also need:
- Heads of terms for the lease or purchase of the land, if you are not the landowner, plus a letter of authority.
- A solicitor’s letter confirming the heads of terms cover the whole site.
- An engineering plan showing all the land in the heads of terms.
- A project timeline with milestones, budget and risks.
For the G99 rules themselves, see G99 explained.
Fees in plain terms
NGED charges assessment and design fees for preparing your offer. The amount depends on how complex the scheme is, and is set out in NGED’s Statement of Methodology and Charges.
- High voltage (11kV) and above: since 1 February 2026, you pay when the offer is issued, even if you never accept it.
- Some smaller offers: the fee is paid on acceptance instead.
- Opt-out: NGED writes to tell you a fee is due. You have 10 working days to withdraw without paying.
- An example: NGED and Regen’s community energy guide (August 2026) quotes about £2,327 + VAT for a 250kW to 1MW project.
How long it takes
NGED’s guaranteed standards (checked 25 October 2026) for a formal offer for generation are:
- Low voltage (LV): 45 working days
- High voltage (HV): 65 working days
- Extra high voltage and 132kV: 65 working days
The clock starts once NGED has all the information it needs. Offers are valid for 90 days. You can ask once for a further 90 days, within the 10 days before expiry, if it does not harm others in the queue. Miss the deadline and you start again.
Connections reform: Gate 1 and Gate 2
Reform changed the queue from “first come, first served” to “first ready and needed, first connected”. It applies to projects 5MW and over, or 1MW and over where the grid supply point has fault level problems. Smaller projects still apply to NGED in the usual way.
- Gate 2 projects show they are ready (land rights, or planning progress for some large schemes) and fit the government’s Clean Power 2030 plans. They get a firm date, connection point and queue place.
- Gate 1 projects are held without firm details. They can only move up during an application window.
For land, you must show rights to 100% of the land the project needs, using NESO’s land-per-MW table. Options generally need at least three years to run.
Where things stand (25 October 2026): NGED is sending Gate 2 offers to existing projects in batches. NESO’s timetable has distribution Phase 1 offers due by mid-November 2026 and Phase 2 offers by mid-March 2027. No date has been set for the first new application window. After that, NESO plans windows twice a year. More in Gate 2 grid offers: autumn 2026 and why a pre-2030 date matters.
What it means now: if your project is 5MW or more, get the land secured and the evidence ready before the window opens. Under 5MW, check your grid supply point. See the 5MW transmission impact threshold.
Interactivity, securities and charges
- Interactivity: if two applications need the same part of the network, both offers become “interactive” and are queued by application date. Whether you can accept depends on the projects ahead of you.
- Connection charges: you pay in full for the cables and kit that only you use. Since April 2023, generation and batteries also pay a share of reinforcement at the voltage they connect at, not the level above. Above £200/kW, the high-cost cap means you can pay more.
- Securities: if your project needs work on the transmission network, you may have to put up security, such as a bond or letter of credit. It covers the cost if you cancel.
- Queue milestones: offers include dates, for example for submitting planning. Miss them and you can lose your place.
Flexible connections and export limits
Where the network is full, NGED can offer an alternative connection. You connect sooner, or for less, but accept limits on export:
- Export limiting: equipment caps your export at an agreed level.
- Timed: you export more at set times of day.
- Soft intertrip: NGED turns you down when a part of the network is near its limit.
- Active network management (ANM): real-time control. NGED plans to have it everywhere by 2028.
The offer sets out the curtailment terms. NGED’s curtailment estimator gives a rough guide.
Common mistakes that delay or kill applications
- Missing heads of terms or solicitor’s letter on projects over 1MW.
- A site plan or red line that doesn’t match the land evidence.
- Asking for more capacity than you need. It costs more and can trigger a transmission assessment.
- Not budgeting for the fee at 11kV and above, or missing the 10-day opt-out.
- Letting the 90-day offer lapse while you think about the cost.
- Ignoring flexible options. An export limit can turn a “no” into a “yes”.
- Missing queue milestones after you accept.
What we do
We prepare and submit grid connection applications and G99 forms for solar, battery and wind developers and larger commercial sites, then chase them with NGED and track every milestone. Most of our fees are published.
Grid consultancy → · Grid application and G99 fees →
Sources
- NGED: connection guaranteed standards of performance
- NGED: types of connection offer
- NGED: connection offer expenses (assessment and design fees)
- NGED and Regen: community energy connections guide (August 2026)
- NGED: connection charging changes from April 2023
- NESO: connections reform timeline
Facts last checked 25 October 2026. Rules, fees and dates change often, so check with NGED before you apply. This is general information, not legal or investment advice.