A solar farm is ready-to-build (RTB) when three things are in place: land rights, a grid connection offer and planning consent. At that point it can be funded and construction can start. RTB is the point most projects are sold or financed.

The three things an RTB project needs

  1. Land rights. An option and lease signed with the landowner, usually for 40 years or more, plus any access and cable routes. What landowners should check.
  2. A grid connection offer. An accepted offer from the network operator, with a connection date and cost. Since grid reform, the date matters as much as the offer itself. Why a pre-2030 date matters.
  3. Planning consent. Permission from the local council, or a national consent for schemes over 100MW. Buyers want the challenge period passed and conditions that can be met.

What else buyers check

RTB is not just three documents. A buyer or funder will also look for:

  • Up-to-date surveys: ecology, landscape, heritage, flood risk, glint and glare. Which surveys are needed.
  • Clean land title: no surprises with tenants, lenders or rights of way.
  • Grid costs and securities that the project can afford.
  • A layout and yield estimate that matches the consent.
  • A tidy data room: every agreement, offer and report in one place.

Gaps in any of these knock value off, or slow the sale down.

Why RTB matters

The further a project gets, the less can go wrong, so the more it is worth. RTB is the highest value point before construction. How RTB projects are valued.

It is also the point where the work changes hands. Developers take the risk up to RTB. Builders and long-term owners take it from there.

How long it takes

With good screening, a site can often reach RTB in around 18 months. The grid date and planning can stretch that. Taking a solar farm all the way to built and generating usually takes two to four years. Full timeline.

What we do

We take solar, battery and wind sites from field to RTB: screening, landowner terms, grid applications and planning, with our own software to track every site. EPC build and maintenance are delivered with partners.

Development to ready-to-build → · Partner with us →

Sources

Facts last checked 25 October 2026. Every site is different. This is general information, not legal or investment advice.